How does the pre-stressing force transmit in post- ...

21 Oct.,2024

 

How does the pre-stressing force transmit in post- ...


Sent: 09-05- 11:56
From: Muhannad Husain
Subject: How does the pre-stressing force transmit in post-tensioning beams/slabs?

Thanks a lot. Quite comprehensive answers.
About the post-tensioning from both sides of a slab, I remember a PT practitioner told me generally it's preferable to stress from both ends (two live ends) had the tendon length exceeded 35 meters long. The longer the tendon, the more friction losses take place. One other reason to stress from both ends is the wobbling effect (as illustrated in the attached figure).

------------------------------
Muhannad Husain S.M.ASCE
Researcher
Hohai University
Nanjing


Original Message:
Sent: 08-31- 05:45
From: Nitin Baraskar
Subject: How does the pre-stressing force transmit in post-tensioning beams/slabs?

The pre-stressing forces in post-tensioning system is transferred at cable ends locations only where they are locked in beams/slabs for resisting tension in the section at given location along the member span. Examples:

a) Bonded cables system (cable ducts are grouted with non-shrinkable cement grout). In bonded system cables are locked at one end termed as dead end if embedded in concrete or fixed end if cables are held in steel plate using steel conical wedges at fixing point. The cables profile are arranged within the section depth to resist the maximum design flexure and tension at given section. Then, cables are pulled from free end would be either one end or both ends to generate the required resisting tension. After attaining the desired forces cables are locked at ends called as anchorage end. The anchorage end/zone are designed for extremely high compression forces generated due to cables pull and locked at ends. The cables are allowed to locked during this stage, meanwhile different losses occurred like slip at wedge, friction offered to cables from ducts and cable profile, etc. Once, cables are locked ducts are grouted to prevent further losses in forces and to protect cables from corrosion.

b) Non-bonded system: cable ducts are not grouted, the forces get transferred to fixed ends where cables are locked.
In case, cables breakage, the provision of dummy cables (4% of total number of cables) is provided to compensate unexpected loss of forces in both bonded and non-bonded pre-stressing post-tension systems.

------------------------------
Nitin Baraskar A.M.ASCE
Senior Engineer
Bechtel India Private Limited
New Delhi ND
+

Original Message:
Sent: 08-30- 07:54
From: Allen Hulshizer
Subject: How does the pre-stressing force transmit in post-tensioning beams/slabs?

Actually this is a general comment regarding Post-Tensioning [PT].

In Nuclear Containment PT construction there is a requirement to check the existing tension load at given periods.

Also, from time to time the PT is released and a section of the wall removed for Steam-Generator replacement and then Re-tensioned.

In a number of cases, when the large wall section has been removed, significant delamination has been discovered. Crystal River was shut down as a result of not being able to resolve the further delamination when re-tensioned.

Any comments on the delamination occurrence and a solution?

------------------------------
Allen Hulshizer P.E., F.ASCE, FACI
Consulting Structural Engineer
Chalfont PA
(215)

Original Message:
Sent: 08-29- 11:32
From: David Thompson
Subject: How does the pre-stressing force transmit in post-tensioning beams/slabs?

I would agree with your concern about transferring tensioning force through friction with large tendons. You just have to look at slippage of strands in pre-stressing after the strands are cut.

There are grouted ducts used in slabs where strands or small tendons are used that my statement would apply.

Our firm has not used unbonded post-tensioning since the 's.  Our concern was the sensitivity of the tensioning system to construction methods and quality leading to corrosion, but that is a different topic

------------------------------
David Thompson P.E., M.ASCE
Principal
KTA Structural Engineers Ltd.
Calgary AB
(403) 246-

Original Message:
Sent: 08-28- 12:27
From: Neil Kazen
Subject: How does the pre-stressing force transmit in post-tensioning beams/slabs?

Original Message:Sent: 09-05- 11:56From: Muhannad HusainSubject: How does the pre-stressing force transmit in post-tensioning beams/slabs?Thanks a lot. Quite comprehensive answers.About the post-tensioning from both sides of a slab, I remember a PT practitioner told me generally it's preferable to stress from both ends (two live ends) had the tendon length exceeded 35 meters long. The longer the tendon, the more friction losses take place. One other reason to stress from both ends is the wobbling effect (as illustrated in the attached figure).------------------------------Muhannad Husain S.M.ASCEResearcherHohai UniversityNanjing Original Message:Sent: 08-31- 05:45From: Nitin BaraskarSubject: How does the pre-stressing force transmit in post-tensioning beams/slabs?The pre-stressing forces in post-tensioning system is transferred at cable ends locations only where they are locked in beams/slabs for resisting tension in the section at given location along the member span. Examples:a) Bonded cables system (cable ducts are grouted with non-shrinkable cement grout). In bonded system cables are locked at one end termed as dead end if embedded in concrete or fixed end if cables are held in steel plate using steel conical wedges at fixing point. The cables profile are arranged within the section depth to resist the maximum design flexure and tension at given section. Then, cables are pulled from free end would be either one end or both ends to generate the required resisting tension. After attaining the desired forces cables are locked at ends called as anchorage end. The anchorage end/zone are designed for extremely high compression forces generated due to cables pull and locked at ends. The cables are allowed to locked during this stage, meanwhile different losses occurred like slip at wedge, friction offered to cables from ducts and cable profile, etc. Once, cables are locked ducts are grouted to prevent further losses in forces and to protect cables from corrosion.b) Non-bonded system: cable ducts are not grouted, the forces get transferred to fixed ends where cables are locked.In case, cables breakage, the provision of dummy cables (4% of total number of cables) is provided to compensate unexpected loss of forces in both bonded and non-bonded pre-stressing post-tension systems.------------------------------Nitin Baraskar A.M.ASCESenior EngineerBechtel India Private LimitedNew Delhi ND+Original Message:Sent: 08-30- 07:54From: Allen HulshizerSubject: How does the pre-stressing force transmit in post-tensioning beams/slabs?Actually this is a general comment regarding Post-Tensioning [PT].In Nuclear Containment PT construction there is a requirement to check the existing tension load at given periods.Also, from time to time the PT is released and a section of the wall removed for Steam-Generator replacement and then Re-tensioned.In a number of cases, when the large wall section has been removed, significant delamination has been discovered. Crystal River was shut down as a result of not being able to resolve the further delamination when re-tensioned.Any comments on the delamination occurrence and a solution?------------------------------Allen Hulshizer P.E., F.ASCE, FACIConsulting Structural EngineerChalfont PA(215)Original Message:Sent: 08-29- 11:32From: David ThompsonSubject: How does the pre-stressing force transmit in post-tensioning beams/slabs?I would agree with your concern about transferring tensioning force through friction with large tendons. You just have to look at slippage of strands in pre-stressing after the strands are cut.There are grouted ducts used in slabs where strands or small tendons are used that my statement would apply.Our firm has not used unbonded post-tensioning since the 's. Our concern was the sensitivity of the tensioning system to construction methods and quality leading to corrosion, but that is a different topic------------------------------David Thompson P.E., M.ASCEPrincipalKTA Structural Engineers Ltd.Calgary AB(403) 246-Original Message:Sent: 08-28- 12:27From: Neil KazenSubject: How does the pre-stressing force transmit in post-tensioning beams/slabs?

Link to Ruiyi

I'm concerned with the statement, "and if the tendons break the effect of the breakage is localized to the area of the break.  The grouting in the tubes allow the force from the tendons to transfer through the grout and then the duct into the concrete. "

What's the development length for a tendon with 200 tonnes (440 kips) PT? How about 900 tonnes ( kips), my heaviest PT to date?


Further, in a tendon of several strands, not all strands are in full touch with the grout.


------------------------------
Neil Kazen F.ASCE
Structural Design Manager Transportation Division
Toronto ON

Original Message:
Sent: 08-27- 11:09
From: David Thompson
Subject: How does the pre-stressing force transmit in post-tensioning beams/slabs?

You are correct that unbonded post-tensioning has forces transferred through wedge action.  This is also true for bonded post tensioning.  The bonding does several things, provides protection to the tendons and if the tendons break the effect of the breakage is localized to the area of the break.  The grouting in the tubes allow the force from the tendons to transfer through the grout and then the duct into the concrete.  The transfer of stressing forces from a broken tendon through the bonded duct is similar to the a pre-stress strand into concrete.

------------------------------
David Thompson P.E., M.ASCE
Principal
KTA Structural Engineers Ltd.
Calgary AB
(403) 246-

Original Message:
Sent: 08-24- 06:56
From: Muhannad Husain
Subject: How does the pre-stressing force transmit in post-tensioning beams/slabs?

------------------------------Neil Kazen F.ASCEStructural Design Manager Transportation DivisionToronto ONOriginal Message:Sent: 08-27- 11:09From: David ThompsonSubject: How does the pre-stressing force transmit in post-tensioning beams/slabs?You are correct that unbonded post-tensioning has forces transferred through wedge action. This is also true for bonded post tensioning. The bonding does several things, provides protection to the tendons and if the tendons break the effect of the breakage is localized to the area of the break. The grouting in the tubes allow the force from the tendons to transfer through the grout and then the duct into the concrete. The transfer of stressing forces from a broken tendon through the bonded duct is similar to the a pre-stress strand into concrete.------------------------------David Thompson P.E., M.ASCEPrincipalKTA Structural Engineers Ltd.Calgary AB(403) 246-Original Message:Sent: 08-24- 06:56From: Muhannad HusainSubject: How does the pre-stressing force transmit in post-tensioning beams/slabs?

Thank you so much for the valuable comments. I may conclude that:

 

-post-tensioned members basically do transfer stresses by means of wedge actions in end zones, regardless the adoption of bonded or unbonded tendons.

-grouting is introduced in bonded tendons as a way of protection only.

 

Am I right?

 

Since the difference between bonded and unbonded is the grout injection, does that mean for two identical beams (same material properties, same prestress applied, etc, but one with bonded and the other with unbonded tendons) the stress distribution and prestress transfer would be nearly the same and follow the same trend?



------------------------------
Muhannad Husain S.M.ASCE
Researcher
Hohai University
Nanjing


Original Message:
Sent: 08-17- 14:14
From: Muhannad Husain
Subject: How does the pre-stressing force transmit in post-tensioning beams/slabs?

It's known that for the pre-tensioned members, the tendons are stressed first and soon the concrete is placed which leads to a (what I call) perfect bonding between the tendon and the surrounding concrete. This achieved bonding is the main key to transfer the stresses. In case of post-tensioning, the tendon is placed through ducts and stressed later after the concrete is poured, which means there's no bond (at least not a perfect one) between the tendon and concrete. So how would the pre-stress transmission work here? I understand that for bonded tendons the grout will help in building that friction between the two surfaces and hence transferring the stresses, but what about the un-bonded ones? Why would we use the un-bonded system?

------------------------------
Muhannad Husain S.M.ASCE
Researcher
Hohai University
Nanjing
+86 183
------------------------------

------------------------------Muhannad Husain S.M.ASCEResearcherHohai UniversityNanjing Original Message:Sent: 08-17- 14:14From: Muhannad HusainSubject: How does the pre-stressing force transmit in post-tensioning beams/slabs?It's known that for the pre-tensioned members, the tendons are stressed first and soon the concrete is placed which leads to a (what I call) perfect bonding between the tendon and the surrounding concrete. This achieved bonding is the main key to transfer the stresses. In case of post-tensioning, the tendon is placed through ducts and stressed later after the concrete is poured, which means there's no bond (at least not a perfect one) between the tendon and concrete. So how would the pre-stress transmission work here? I understand that for bonded tendons the grout will help in building that friction between the two surfaces and hence transferring the stresses, but what about the un-bonded ones? Why would we use the un-bonded system?------------------------------Muhannad Husain S.M.ASCEResearcherHohai UniversityNanjing+86 183 ------------------------------

Advantages of Post Tensioning

5 Unexpected Advantages of Post-Tensioning

Since the s, post-tensioning concrete has grown in popularity. Whether you&#;re trying to streamline the building process, reduce costs or give a structure the best chance of surviving weather hazards, there are numerous benefits of post-tension slabs.

Here&#;s a look at some hidden advantages of post-tensioning concrete and why you should consider these methods for new structures.

What Is Post-Tensioning?

Post-tensioning concrete is the process of adding steel bars (tendons) below a mixture&#;s surface. Once the concrete fully cures, tension is applied to the steel bars. These reinforcements introduce stress to the concrete, which can prevent cracks and shifting down the road.

For more post tensioning system servicesinformation, please contact us. We will provide professional answers.

Construction teams rely on post-tensioning methods to help concrete reach its strongest state. This process is efficient for creating surfaces that can withstand the loads required for a newly developed structure.

Benefits of Post-Tensioning

Consider these surprising advantages of post-tensioning.

1. Saving on Costs and Materials

Prestressed concrete supports larger loads compared to traditional pouring. Using post-tension methods means concrete substrates are thinner, sometimes by as much as 20%.

When a building is complete, the total height of the structure is shorter than constructing slabs without post-tension reinforcements. Smaller buildings call for teams to use less cladding, concrete, cement and shear. Extra materials can be used for future projects or returned to the manufacturer to increase your bottom line. Either way, you&#;ll save on costs and materials.

2. A Sustainable Approach to Building

When you rely on post-tensioning concrete methods, fewer materials are involved in the final structure. This includes the amount of cement used to create concrete mixtures &#; a significant source of carbon emissions.

It&#;s possible the timeline for a building project will be shorter with post-tensioning concrete, which lessens the amount of time gas-powered tools and vehicles run from the start of the assignment through completion.

3. Efficient Construction Timelines

The setup for post-tension procedures can be done quickly without the variables of traditional curing. The fact that crews spend less time laying steel supports means teams will be ready to pour mixtures and let the concrete dry on an impressive timeline. Your post-tension building project can progress consistently.

4. Crack Control

Post-tensioning results in compressive stress in concrete, which helps to reduce the effects of shrinkage and temperature changes that can cause cracking. The post-tensioning system consists of steel strands that are tensioned after the concrete has hardened, creating internal forces that resist external loads.

Post-tensioning systems are effective for crack control because the tendons act as reinforcement for the concrete and prevent it from splitting apart. The tendons are anchored at both ends of the concrete member and are usually placed in ducts or sleeves to allow them to move freely during tensioning.

The tendons are tensioned by hydraulic jacks and then locked in place by wedges or nuts at the anchorages. The tension in the tendons induces a compressive stress in the concrete, which counteracts the tensile stress caused by shrinkage or bending. This way, the concrete remains relatively crack-free and watertight throughout its service life.

5. Better Performance

Many property owners building post-tension structures find surfaces do a fantastic job of limiting unwanted vibration and sag. Inside the poured concrete, cables help to balance the load.

Rather than the center of slabs being put under immense stress where they can crack, the internal cables take care of the heavy lifting. Over time, concrete maintains its shape and refrains from dipping downward when objects are placed on top of it.

About Post-Tensioning Products and Services From STRUCTURAL TECHNOLOGIES

STRUCTURAL TECHNOLOGIES provides VSL post-tensioning products as well as construction systems in the United States. Whether you want to build or repair a commercial building, parking lot or similar structure, we will assist with design, installation and material fabrication for unbonded monostrand post-tension systems, bonded multistrand post-tension systems, shear reinforcements, barrier cables and lockable dowels.

We specialize in external and internal post-tensioning technology. STRUCTURAL TECHNOLOGIES provides you with solutions for installations outside a structural element &#; within grouted ducts &#; or within an existing member &#; via core drilling &#; to handle the scope of your project.

Get Started With Post-Tensioning Today

To learn more about post-tensioning products and our service capabilities, submit a contact form with STRUCTURAL TECHNOLOGIES.

For more information, please visit post tensioning system supplier.